Changeset 2856


Ignore:
Timestamp:
May 12, 2006, 3:06:56 PM (18 years ago)
Author:
sexton
Message:

updates

File:
1 edited

Legend:

Unmodified
Added
Removed
  • documentation/planning/priorities.tex

    r2833 r2856  
    6464    with ill-conditioned system as a result of a complex internal
    6565    polygon. Whilst a protection has been put in place for friction
    66     creep, the issue is still outstanding. The ill-conditioned nature
    67     of the system remains an outstanding issue and is related to the
    68     conjugate gradient solver not converging. Final results will be
    69     delivered to Benfield by Fri 28 April noting the latter two issues
    70     are still outstanding.  This project has synergies with the ANUGA
     66    creep, the issue is still outstanding. Final results will be
     67    delivered to Benfield by Fri 28 April noting the friction issue
     68    is still outstanding.  This project has synergies with the ANUGA
    7169    Demo initiative (Everyone)
    7270  \item Port Hedland - end of June 06. Also part of the WA project. (Nick)
     
    124122    \item Boxing day event (ANU contract 2006/2007 with Asavanant and Grilli)
    125123    \item Friction validation (Duncan with Tom Baldock UQ)
    126     Duncan to get a sense of scope on this by June 2003.
     124    Duncan to get a sense of scope on this by June 2006.
    127125    Work to be done in 2006/2007.
    128126    \item PDC (Ole)
    129127    Ole to visit Pacifit Disaster Center in 6/7
    130     \item 1953 Suvadata from Tariq (someone)
     128    \item 1953 Suva data from Tariq (someone)
    131129    Date is available. Ole to arrange for unpacking with GIS and scope project.
    132130    Could form a graduate project.
     
    135133  \item Momentum sink study (Duncan with Nick Dando)
    136134  Report and talk by end of June 2006. Paper later.
    137   \item Submarine landslide modelling paper with Dr Mueller or Russell Blong (Ask him), Sydney (Jane, Ole, Adrian, Matt). Perhaps use Wollongong as the study area. 
     135  \item Submarine landslide modelling paper with Dr Mueller or Russell Blong (Ask him), Sydney (Jane, Ole, Adrian/Monica, Matt).
     136        Perhaps use Wollongong as the study area. 
    138137  \item Probabilistic integration with URS model, pending URS data (Ole, Trevor).  Ask PDC. 
    139   \item Effect of the GBR based on new LADS data (which we need to get from Phil O'brien). This could become a graduate program, an ANU contract or a job for an ANU summer scholar.
     138  \item Effect of the GBR based on new LADS data (which we need to get from Phil O'brien).
     139        This could become a graduate program, an ANU contract or a job for an ANU summer scholar.
     140  \item Comparing calculated run-up height with Synolakis' approximation
     141        ($R = A^\frac{4}{5} h^ \frac{1}{5}$ where $A$ is the amplitude at some offshore location
     142         and $h$ is the depth at the same offshore location). Calculate the maximum elevation
     143         at which there is water. Need to confirm definition of run-up height.
     144  \item Incorporate asteroid model (parabolic cavity) as an initial condition into ANUGA.
     145        Compare calculated extent with the approximation of
     146        run-in (or maximum extent) from Chesley and Ward 2006 where the run-in distance is approximated
     147        by $X \approx 10 \sqrt{g R} D^\frac{3}{8}$ where $R$ is the run-up height and $D$ is the
     148        asteroid diameter. Allows another event to be added to the overall
     149        tsunami risk assessment. This could become a graduate or student project.
    140150  \item Scenario database (future); this could complement the ATWS
    141151    operational centre. (how often would it need to be updated, i.e how
     
    230240\subsection*{Earthquake and Tsunami Hazards (ETH)}
    231241\begin{enumerate}
    232   \item \textbf{David Burbidge}: Link to URS data
     242  \item \textbf{David Burbidge}: Link to URS data; developing probabilistic hazard map
    233243  \item \textbf{Phil Cummins}: Team leader
    234244\end{enumerate}   
     
    302312\begin{itemize}
    303313  \item \textbf{Duncan}: 4 days/week
    304   \item \textbf{Jane}: Leave from 15 June 2006 to 15 July 2006
     314  \item \textbf{Jane}: Three weeks leave in the period 15 June 2006 to 15 July 2006
    305315    Ole to cover Jane's commitments.
    306316  \item \textbf{Nick}: Leave from 22 August 2006 to 13 October 2006
    307317    Duncan to cover off on the production line.
    308318  \item \textbf{Ole}: Leave for six weeks around August or September.
    309     Jane to be acting team leader.
     319    Jane to be acting team leader with Duncan responsible for
     320    software and maintenance issues.
    310321\end{itemize}
    311322